November 5, 2026
"You had to have a well before you could do anything," a longtime Kanis Road resident told KARK in February 2024, the day Central Arkansas Water announced it was finally extending service into Ferndale. A Central Arkansas Water representative told the station the project had "been in the works for two decades plus."
The pipe has been arriving since then, one road at a time. It also comes with paperwork that a listing sheet doesn't show. If you're comparing acreage out here, one of the most useful questions about a parcel is which road it sits on, and where that road falls in the utility's phase schedule.
Public water in Ferndale doesn't work like a standard hookup in Chenal Valley. Central Arkansas Water signed people up through a West Pulaski water service contract, and the 2021 version spells out terms that go beyond a normal utility bill:
The contract also says Central Arkansas Water will review surcharge collections at least every 60 months until the debt is paid, and lower the charge if the financing terms allow. That makes the $125 figure a ceiling written into a 2021 form, not a fixed rate for every address.
Today, the utility's West Pulaski sign-up page is still taking applications from residents in unserved parts of western Pulaski County. It links to a newer, general water service contract. That form says service is subject to Central Arkansas Water's rates, rules and regulations, "now and in the future."
The surcharge exists because of how the project is paid for. Central Arkansas Water's board packets describe the funding stack the same way each time a new phase comes up for a vote:
| Funding piece | Amount listed |
|---|---|
| EPA grant, Federal Direct Allocation | $12 million |
| American Rescue Plan Act grant | $5 million |
| Arkansas Natural Resources Commission loan, principal forgiveness | $2.2 million |
| Arkansas Natural Resources Commission standard loan | Repaid "from an area surcharge from those served by the project" |
Grants and a forgivable loan carry part of the cost. The board packets say the standard loan is to be repaid from an area surcharge from those served by the project. The utility's general rate page says Central Arkansas Water has no debt-service charge for its own system and handles debt-service billing for other districts separately.
The surcharge looks like a lot to some owners. In the same KARK report, another resident said he'd been told the charge would be $125 a month plus usage. He said he would sign up only if the price came down to a level he considered suitable. The utility said then that it knew not everyone would sign up, but that access would be there for those who wanted it.
The full buildout covers about 55 miles of water mains, from 16-inch down to 3-inch, mostly running along existing roads. It's being bid in pieces, and every piece needs its own board vote:
| Phase | Where it runs | Size | Board action |
|---|---|---|---|
| 1A | First segment bid | Not specified | Bid before Phase 1B |
| 1B | From Kanis Road and Ferndale Cutoff south to the 4-H Center | 1.2 miles | Agenda item, March 14, 2024 |
| 2A | Includes Whispering Woods Road via change order | 2,218 added feet on Whispering Woods | Awarded August 2025; $298,922.70 change order on the November 13, 2025 agenda |
| 2B | Ferndale Cutoff from Kanis to Studer Road; Bush Mountain Trail; rest of Walnut Grove between Kanis and Burlingame | 3.5 miles | $3,294,825.35 contract with Diamond Construction recommended May 14, 2026 |
| 2C | Portions of Garrison Road, Jones Loop, Sword Lane and Deer Drive | 4.8 miles | $2,494,917 contract with Diamond Construction recommended September 10, 2026 |
| 3 | Later segments, including areas labeled 3A through 3D | Not specified | $703,112 engineering amendment, February 12, 2026 |
Add up the phases with listed lengths and you get under 10 of the roughly 55 planned miles. Halff Associates designs and bids the phases, with approvals from the state's Natural Resources Division and the Arkansas Department of Health.
Some phases do more than serve the homes along them. The utility's May 2026 board packet says Phase 2B connects the sections built in Phase 1 and Phase 2A. That closes a gap in the West Markham pressure zone and creates a looped system "for resiliency and redundancy." The Bush Mountain Trail segment also extends the Paron system to the new West Pulaski Fire Department station. Phase 2C includes fire hydrants along with the pipe.
Picture two 10-acre tracts a few miles apart on either side of Kanis Road. Their soil, frontage and views are similar, and so are their asking prices. One sits on a road named in a phase that has already gone to the board for a construction contract. The other sits in a segment the utility's map still labels "future phase."
Their buyer pools differ. The parcel on a well depends on what's under it. An EPA environmental document on the project says the Ferndale and West Pulaski area had no municipal water. Residents relied on private wells whose quality and quantity were unknown. The same document cites a 2008 sampling study in which 41 of 74 valid well samples showed coliform contamination.
Most rural markets price land by acreage, road frontage and topography. In Ferndale, a fourth factor is now on the list, and it moves on the utility's schedule, not the market's. A road gets water when grant money, a low bid and a board vote line up, and the next segment waits for the next round. A parcel on a "future phase" road could move up the schedule with one agenda item.
Questions about a specific address include:
Utility contracts and surcharges carry real obligations, and this post is general information, not legal or financial advice. Confirm the terms for your specific parcel with Central Arkansas Water and with your attorney or lender before you rely on them.